Justin Pedley acted as Project Director for Port Metro Vancouver (PMV) who is delivering the project on behalf of four funding partners (PMV, Transport Canada, CN, and CP).
The $75M, linear civil project on Port land on the South side of the Burrard Inlet enhances and improves the Port road and rail capacity to allow for the expected 30% increase in bulk commodities and 70% increase in container traffic that is expected on the South Shore.
Key elements of the project include:
Construction of an 800m long elevated roadway between Clark Drive and Victoria Drive to grade separate 10 road-rail at-grade conflicts.
30m pedestrian overpass at Victoria Drive.
A 1500m realignment and widening of Commissioner St
An upgrade and rebuild of 3 Port entrances at Heatley Drive, Clark Drive and Commissioner Street
Improvements to two City intersections at Commissioner/McGill and Commissioner/New Brighton
Upgrades to Port operational and security control systems including CCTV and Vehicle Access Control systems (VACS)